Estinnes Eco Solar Park
Project details
Location: Estinnes-au-Val – Terril du Levant (Mons)
Capacity: 12 MW
Grid Operator: ORES
Commissioning: End of 2025 (planned)
HOP is acting as the electrical expert for the eco solar park being built on a former mining site in Estinnes.
We tested the ORES RTU and disconnection relay in conjunction with the park’s PLC to ensure safe grid integration. Coordination with other contractors is closely monitored to safeguard project quality.