Péronnes-lez-Binche Solar Park
Project details
Location: Péronnes-lez-Binche
Capacity: 7.8 MW
Grid Operator: ORES
Commissioning: May 2025
HOP played a key role in the successful commissioning of the solar park in Péronnes-lez-Binche.
We delivered the full AC dossier, managed the transformer deliveries, and configured the PLC settings. The ORES RTU and disconnection relay were tested together with the park’s PLC to ensure safe operation.